As the OASIS development team addresses and enhances the data migration work, along with incorporating key changes identified during the IAQG Spring 2022 Meeting Week, the project has seen adjustments to critical paths in our timeline to launch. While we continue to refine the dates, below is the most current timeline given the facts we know today.
- Middle of August – Completion of a final, full data migration test that will confirm the system freeze timeframe prior to launch.
- Middle-to-end of August – final data integrity testing from IAQG testing teams representing all user roles within OASIS.
- End of August: Anticipated 30-day notice of OASIS V3 launch
- Middle-to-end of September: Launch OASIS V3 with a freeze period (approximately 3-5 days) of the current platform prior to launch
As a reminder, the current OASIS will remain open and available until the freeze date, at which time it will move to a read-only format.